Performance-based Contracting for Roads in Chad
| 1. Country |
Chad |
2. Year when PBC was first
launched
|
The first contract execution started in June 2001. |
| 3. What government organization
promoted/initiated a PBC approach in the country? |
Minister of Public Works and Director of Roads |
| 4. What were the reasons for
switching from the traditional unit price-based to performance-based
contracts for road maintenance? |
In 90s they switched from the force account to the private
sector; but they were not satisfied with the results they were
paying for and they decided to pay for the level of the service
instead of inputs.
Another reason was a financing issue, as the Ministry of Public Works and National
Road Directorate saw that the donors would participate in financing this type
of contract. |
| 5. Name of the organization currently
in charge of management of road maintenance |
National Road Directorate |
| 6. Supervision of the contractors
is done by |
International consulting firm from Cameroon, employing local
staff |
7. Sources of the current funding
of PBC
(in %) |
External
funding – 80% (WB)
Central
government funding – 20% |
| 8. Unit cost per km per year |
USD 5,700 per km per year (including rehabilitation, periodic
and routine maintenance) |
| 9. Typical contract cost (USD)
and duration (years) |
The contract cost was USD 22,800.
The duration was 4 years. |
| 10. Typical contract cost (USD)
and duration (years) with the supervisor |
The contract with the supervisor started a month-two earlier
than that with the contractor, but it covered the same time period. |
| 11. Dispute resolution mechanism |
Adjudication (e.g., Dispute Review Expert): an international
expert from France was involved |
| 12. Procurement process |
International Competitive Bidding |
| 13. Degree of competition |
Two international and one national contractor were selected
during the prequalification.
The local contractor lost because its contract price was 12% above the engineer’s
estimate.The winning bid was 7% below the engineer’s estimate. |
| 14. What contractor selection
criteria were used during the bid evaluation and what weight
did they
have during the bidding evaluation |
The contract price weight was 100% |
| 15. Types of delivery services
under lump sum payment |
Rehabilitation and maintenance |
| 16. Types of roads covered under
PBC and their pavement type |
440 km of national, all unpaved, fewer than 100 vehicles per
day, but 60% of this traffic are usually heavy trucks. This section
is an important strategic road, as it connects East and West
of the country and main access centers. |
17. Percentage of this type
of road in the entire network under PBC
|
Total
all-season roads: 2,600 km
Under
PBC: 440 km or around 17% as of 2005 |

Context
Due to poor results with traditional road maintenance contracts and
insufficient mobilization of domestic funding for maintenance,
Chad’s government decided to pilot a new type of contract,
which would allow improving the road conditions at a lower price
than the price of traditional method-based contracts.
Bidding process
In late 2000 a competitive international tender was launched to implement
a four-year PBC to manage and maintain 441 kilometers of unpaved
main roads, which represented 7% of the primary network. The contract
covered sections previously passable only during the dry season.
Three bidders were selected during the pre-qualification. The submitted
bids were evaluated on the basis of a monthly lump-sum fee required.
The winning bid price was 7% lower than the engineer’s estimate.
Implementation of the contract
The execution of the contract started in July 2001, three months
after signing the contract. The contractor was given 22 months
to bring a service quality up to the required levels. The contract
was completed in June 2005.
The up-front payment was provided in the amount of 20% of the contract
value, for which the contract had to provide a guarantee. The contractor
provided a performance security of 10% of the contract value.
The contractor is paid a monthly fee - $480 per km - in case of
compliance with performance indicators. The fee covers, among other
things, a complete rehabilitation of the road at the project outset,
management and maintenance of the road for four years, self-monitoring
of compliance with the performance criteria, and provision of the
basic services in road accidents.
Performance indicators and monitoring of compliance
A consulting firm from Cameroon was contracted out to perform the
surveillance of the contract. Two monitoring mechanisms were designed
to evaluate the contractor’s performance and compliance with
the service criteria. The first one is the contractor’s self-monitoring
with the consequent submission of a report with each monthly invoice
to the client; and the second one is verification of the contractor’s
reports by the consultant through monthly inspections. In case
of non-compliance with any of the service criteria in any month,
the monthly fee is reduced. If non-compliance occurs repeatedly,
the contract can be suspended.
The service criteria against which the contractor’s performance
was evaluated include:
passability
(the road must be open),
average speed
attainable,
user comfort,
and
durability
(a measure of the long-term sustainability of the road).
Results
Since the contractor met and in many cases exceeded the performance
specification defined in the contract, the roads were returned
in excellent condition. “Road users appreciate that the road
is always in good conditions and not only after specific works
were completed. Especially important is that they can use the road
in the rainy season, which was impassable before” (Zietlow
2004).
The successful outcome regarding the road quality has led to a criticism
that indicators may have been set too high.
Directions for future
According to some sources, Chad’s government planned to either
extend or re-bid the contract for another 4 years after it expired
in June 2005. Renewal would be based on a lower price, since the
contractor has completed the initial rehabilitation requiring large
up-front investments. In addition, the government is keen on letting
another contract for 650 km of paved roads, which link key centres
in Chad and Cameroon.
Sources:
- Interview with A. Schliessler, Senior Transport Economist for
the Transport Unit in the Africa Region and Task Team Leader
of the Chad National Transport Support project. March 2005.
- Hartwig, T., Mumssen, Y. and Schliessler, A. 2005. “Output-based
Aid in Chad: Using Performance-based Contracts to Improve Roads.” Global
Partnership on Output-based Aid. Note No 06.
Washington, D.C.:
World Bank. Courtesy of GPOBA.
Also available at: http://www.gpoba.org/documents/Chad_Roads_OBApproaches.pdf
- Zietlow, G. 2004. “Implementing Performance-based Road Management
and Maintenance Contracts in Developing Countries – An Instrument
of German Technical Cooperation.” November 2004.
Eschborn,
Germany. Courtesy of G. Zietlow.
Also available at: http://www.zietlow.com/docs/PBMMC-GTZ.pdf
Back to Case
Studies

|