wbg_psd.gif (769 bytes) 1bfree.gif (1368 bytes)
1bleft.gif (932 bytes) 1bright.gif (969 bytes)


gasturbine.gif (5474 bytes)

gasturbine_table.gif (6992 bytes)

Charles McGowin, Evan Hughes & Neville Holt, EPRI

The potential of the biomass gasification combined cycle (BGCC) approach for efficient and fuel-flexible use of biomass for power generation led the Global Environment Facility (GEF) and The World Bank to consider a pilot demonstration program in Brazil

As part of Phase II the World Bank contracted EPRI to undertake an economic and risk evaluation of the Brazil BIG-GT project. The risk evaluation perfumed by EPRI was conducted in order to assess whether biomass gasification/combined cycle technology will eventually become competitive with other new and evolving electricity supply resources available in northeastern Brazil.

The results of the evaluation are described.

The Brazil Project

Brazil Biomass Integration Gasification – Gas turbine (BIG-GT Project)

The potential of the biomass gasification combined cycle (BGCC) approach for efficient and fuel-flexible use of biomass for power generation led the Global Environment Facility (GEF) and The World Bank to consider a pilot demonstration program in Brazil. Earlier studies by Princeton University and Companhia Hidroeletrica do Sao Francisco (CHESF) indicate that development and commercialization of reliable and efficient biomass gasification-combined cycle technology could make it possible to develop considerable electricity supply capacity in northeastern Brazil at costs below the marginal system costs (Ref. 1). The electricity supply potential is estimated to be about 20,000 MWe.

Project Objectives

The key development objectives of the Brazil BIG-GT project are:

Short-term objective: To establish a globally-replicable prototype unit on a commercial scale for the cogeneration of electricity based on the gasification of wood chips or sugarcane bagasse. No native forests will be used in fulfilling this objective.

Long-term objective: To reduce global warming by lowering CO2 emissions from fossil fuels which would be produced by conventional thermal generation.

The environmental and social objectives of the project include employment and income growth in rural areas, sustainable development, increased private capital investment in the power sector, economic support to industries that already use biomass, verification of the benefits of afforestation for energy production and decentralized electricity generation, and creation of long-term programs for wood and sugarcane production.

It is anticipated that covering up to five per cent of the land area of northeastern Brazil with energy plantations would generate $1.7 billion of investment capital, result in construction of 10 to 20 BIG-GT power plants each year, and create 12,000 new jobs per year needed to develop, operate, and maintain the energy plantations and power plants.

Conceptual designs and cost estimates were produced for two different biomass gasification technologies in combination with the General Electric LM-2500 aeroderivative gas turbine:

(1) the atmospheric fluidized bed combustion gasification technology offered by TPS Termiska Processor AB, using cold quench wet scrubbing to clean up of the product gas; and

(2) the pressurized fluidized bed gasification technology offered by Bioflow, a joint venture between A. Ahlstrom Corporation in Finland and Sydkraft AB of Sweden, using hot gas ceramic filters to clean up the product gas.

Phase I resulted in the selection of the TPS Termiska atmospheric fluidized bed combustion technology for the project (Ref. 2).

Economic and Risk Evaluation

As part of Phase II the World Bank contracted EPRI to undertake an economic and risk evaluation of the Brazil BIG-GT project. The risk evaluation perfumed by EPRI was conducted in order to assess whether biomass gasification/combined cycle technology will eventually become competitive with other new and evolving electricity supply resources available in northeastern Brazil.

The overall objective of the risk evaluation was to assess: (1) the impact of World Bank/GEF funding of the Brazil biomass gasification demonstration project on the commercialization timetable of the technology; and (2) the likelihood that biomass gasification/combined cycle technology will ultimately deliver power to northeastern Brazil at a lower cost than other new and evolving candidate electricity supply options.

The risk evaluation by EPRI included the following: (1) Identification of the candidate electricity supply options for the northeastern region of Brazil; (2) deterministic analysis of the levelized delivered cost of electricity for each of the supply options; (3) probabilistic analysis of biomass gasification-combined cycle technology; and (4) decision analysis of the World Bank decision about whether to fund the Brazil BIG-GT demo project.

The results indicated that biomass gasification, biomass combustion, and wind turbines are likely to be competitive with other candidate power supply options in northeastern Brazil after 2010, including oil- and gas-fired combined cycle, coal gasification, gas- and oil-steam, hydro, and native and imported coal-steam. The decision analysis indicated that the present value savings of a decision by the World Bank to fund the project could reach $200 to $400 million in 2010, relative to a decision not to fund the project. This assumes that the experience gained in the demo project would lead to use of more advanced technology to build ten or more 100MW biomass gasification plants in 2010 and each plant would realize life cycle present worth savings of $20 to $40 million.

BIG-GT Demonstration Plant Process Description

The proposed BIG-GT demonstration plant will generate approximately 40 MW of electricity and deliver approximately 32 MW of electricity to the grid. The wood feed is chipped and dried (using waste heat)on-site. The dried wood chips are fed to the air-blown fluidized bed gasifier (1.8 bar). The wood chips and residual char are suspended by the upward flowing air injected at the bottom of the gasifier vessel and by the product gases released by the gasification reactions. Solids that are entrained with the product gases leaving the vessel are separated and removed by a cyclone separator and reinjected into the gasifier.

Before passing to the gas turbine, the product gas is subjected to a series of conditioning steps to remove tars, ammonia, and fine particulate that could damage or otherwise adversely affect the gas turbine, including tar cracking, quench scrubbing and gas compression.

figure1.gif (46761 bytes)

Figure 1. Process Schematic of TPS Termiska Atmospheric Pressure GIG-GT Demonstration Project (Ref. 3)

Demonstration Plant Performance

Table 1. Projected Performance and Fuel and Auxiliary Power Consumption

 

Units

Quantity

%

Plant Performance
Gross Capacity

MW

40.40

100.0%

Auxiliary Power

MW

8.14

20.1%

Net Capacity

MW

32.26

79.9%

Annual Capacity Factor

%

85%

Annual Generation

MWh/yr

240,208

LHV Basis

HHV Basis

Net Thermal Efficiency

%

40.7%

38.0%

Net Plant Heat Rate

kJ/kWh

8,848

9,473

Btu/kWh

8,389

8,982

Biomass Heat Content

GJ/dry m ton

18.4

19.7

MBtu/dmt

17.4

18.7

Fuel Consumption

Hourly

Annual

Biomass Fuel

dry m ton

15.52

115,562

LPG

kg

6.0

44,700

Diesel Oil

m ton

0.10

72

Auxiliary Power Cons.
Gas Compression

MWh

4.90

36.5

BOP

MWh

3.24

24.1

Table 2. Projected Cost of Wood Stumpage, Harvesting, Transport, and In-Plant Handling and Chipping

Cost Item

US $/m ton (0% m)

US $/GJ

US $/MBtu

% of Total

Price of Wood on the Stump

$13.75

$0.70

$0.74

35.6%

Price of Cutting

6.19

0.31

0.33

16.0%

Price of in Field Transport

5.57

0.28

0.30

14.4%

Price of Cut Wood in the Field

$25.51

$1.29

$1.37

66.0%

Price of Loading

4.02

0.20

0.22

10.4%

Price of Freight

4.33

0.22

0.23

11.2%

Price of Wood at Gate before ST

$33.86

$1.72

$1.81

21.6%

Social Tax

0.21

0.01

0.01

0.5%

Social Tax

0.69

0.03

0.04

1.8%

Price of in Plant Wood Handling

$34.75

$1.76

$1.86

2.3%

Price of in Plant Wood Handling

0.89

0.05

0.05

2.3%

Price of Wood Chipping

2.96

0.15

0.16

7.7%

Total Price of Wood Delivered
to Dryer

$38.60

$1.96

$2.07

100.0%

Table 3. Fuel and Fixed and Variable O&M Costs (85% capacity factor)

Annual Cost

$/kW-yr

$/MWh

% of Total

Wood Fuel

$3,936,981

$122.0

$16.39

52.3%

Auxiliary Fuel
LPG

$15,960

$0.49

$0.07

0.2%

Diesel Oil

$338,037

$10.48

$1.41

4.5%

Total

$353,997

$10.97

$1.48

4.7%

Variable O&M
Dolomite/Areia

$250,383

$7.76

$1.04

3.3%

Chemicals

89,643.44

2.78

0.37

1.2%

Lubricants

28,597.93

0.89

0.12

0.4%

Fuel Handling

250,915.90

7.78

1.04

3.3%

Ash Disposal

43,169.39

1.34

0.18

0.6%

Total

$662,709

$20.54

$2.76

8.8%

Fixed O&M

$2,567,162

$79.6

$10.69

34.1%

Total O&M and Fuel

$7,166,853

$233.1

$31.31

100.0%

Results of the Risk Evaluation

EPRI used their "BIOPOWER" spreadsheet model for sensitivity analyses to determine the parameters most critical in determining the economics and the risks associated with biomass gasification power generation technology. A "Tornado chart" (Figure 3) displays the relative importance of various technical and economic parameters in changing the cost of the electric energy generated by the BIG-GT power system.

The dominant parameters are total plant cost (i.e., the capital cost), the discount rate (a non-technical, purely economic factor, not directly related to the technology itself), and the availability/capacity factor (CF). The ranges of change in the cost of electricity (COE) shown in Figure 3 are derived from both the judgement of the likely range in the value of the parameter involved (e.g., total plant cost from a low of $1830/kW to a high of $2180/kW for the year 2000 case) and from the importance of (i.e., sensitivity to) that parameter in the overall economic model that calculates the cost of electricity (COE). In Figure 3, cost of electricity is expressed in $/MWh above or below a base case cost of $92/MWh in the year 2000.

These results were then used in a probabilistic model to calculate cumulative probability distribution functions for the COE in various future years as the technology improves. (Figure 4 and Table 4)

Finally a decision analysis calculation was made to estimate the benefits in risk reduction, and the related cost reduction, associated with the World Bank and GEF continuing to cosponsor the Brazil biomass gasification power system project.

Figure 2. Tornado Chart

figure2.gif (8687 bytes)

Figure 3: Cumulative Probability

figure3.gif (9651 bytes)

 

Table 4:

table4.gif (24580 bytes)

Decision Analysis

The decision analysis addressed the potential outcomes of two alternate World Bank decisions regarding funding of the Brazil BIG-GT demonstration project:

1. World Bank decides to fund the demonstration project.

2. World Bank decides not to fund the demonstration project.

The decision analysis addressed the levelized delivered cost of electricity (COE)for a 100 MW commercial biomass gasification power plant, constructed in northeastern Brazil soon after 2010. The analysis focused on: the likely impact of the possible World Bank funding decisions on construction of the demo plant; the resulting experience gained by Brazilian scientific, agricultural, and industrial community; the capability to construct, operate, and maintain a power plant using advanced technology in both Brazil and other developing countries; and the resulting levelized delivered COE.

Figure 4 presents the decision tree developed for the decision analysis. The decision tree displays the structural relationship between the decisions, World Bank Funds Project, and World Bank Doesn’t Fund Project, and the uncertainty variables, State of Technology used in 2010, Total Plant Cost, Biomass Fuel Cost, and Annual Capacity Factor.

The State of Technology used in 2010 variable characterizes the impact of the World Bank funding decision on the technology used to build a commercial plant in 2010. It was assumed that a decision to provide World Bank funding of the project would provide the capability for Brazil to develop and use more advanced technology in 2010 (possible outcomes: use 2020, 2015, or 2010 technology in year-2010 commercial plants). Conversely, a decision not to provide World Bank funding would make it difficult for Brazil to use even the technology expected to be commercially available in 2010 (possible outcomes: use 2010, 2005, or 2000 technology in year-2010 commercial plants).

Each branch of the tree represents a specific combination of the four uncertainty variables, and all possible combinations of the variables are addressed. There is one node associated with each uncertainty variable. Each node has three branches, each corresponding to three values of the uncertainty variable and probabilities of occurrence.

The decision tree was used to develop the cumulative probability distributions of the levelized delivered cost of electricity in 2010 shown in Figure 5, one for each potential World Bank decision.

Key Findings

  • The cumulative probability curves suggest that, if the World Bank decides to fund the Brazil Biomass Integrated Gasification/Gas Turbine Project, the expected levelized cost of electricity of a biomass gasification power plant will be about $12/MWh lower for plants built in 2010, than if the decision is made not to provide the funding.
  • The rationale is that the demo project would provide significant experience and know-how to the Brazilian scientific, technical, agricultural, and industrial communities. As a result, the project participants would be capable of building, operating, and maintaining a more advanced and lower cost commercial plant in 2010 than if the demonstration project does not go forward.

Figure 4. Decision Tree for World Bank Decision Analysis of Brazil Biomass Integrated Gasification/Gas Turbine Demo Project

figure4.gif (8838 bytes)

 

Figure 5. Cumulative Probability Distributions Levelized Delivered COE vs. World Bank Funding Decision Outcome

figure5.gif (7728 bytes)

Implications

  • For a single 100 MW plant operating at 85% capacity factor, the $12/MWh levelized delivered COE savings resulting from a World Bank decision to fund the Brazil BIG-GT demo project translate to annual savings of $8.8 million/year.
  • Assuming a 12%/yr discount rate, the cumulative 25-year present-value savings are $69 million in 2010, or $22 million after discounting back to the year 2000. At 8%/yr discount rate the cumulative 25-year present value savings total $95 million in 2010, or $44 million in 2000.
  • By accelerating the progress toward commercializing biomass gasification technology and by communicating that progress to the world, the Brazil BIG-GT demonstration project would likely make it possible for ten such 100 MWe-scale plants to be installed worldwide in 2010.
  • As a result, the total world-wide savings resulting from the Brazil project would probably be at least an order of magnitude higher, i.e. at least $220 to $440 million after discounting back to 2000.

Conclusions

• The Brazil Biomass Integrated Gasification-Gas Turbine (BIG-GT)demonstration project would play an important role in the progress toward lower cost biomass power, especially in developing countries.

• The experience gained in the project by the Brazilian scientific, technical, agricultural, and industrial communities would provide the know-how and capability to use more advanced technology and probably accelerate the introduction of commercial biomass gasification-combined cycle power plants in Brazil after the year 2000.

• The deterministic analysis suggests that biomass gasification and direct combustion power plants offer potential to supply electricity to meet the growing power demand in northeastern Brazil after the year 2000 at a delivered life-cycle cost that is lower than or competitive with the cost of all other candidate electricity supply options, including natural gas-combined cycle.

• The probabilistic analysis of biomass gasification combined cycle power plants suggests that there is a high probability that biomass gasification and direct combustion power plants will deliver electricity to northeastern Brazil at a cost that is lower than or competitive with the cost for all other electricity supply options after the year 2010.

• The decision analysis of the World Bank funding decision suggests that World Bank funding will contribute significantly to Brazil’s capability to deploy biomass gasification power plants in Brazil after the year 2010 and would reduce the delivered cost of electricity from the plants.

References

1. Elliott, Philip and Roger Booth, "Brazilian Biomass Power Demonstration Project", Special Project Report, Shell International Petroleum Company, London, 1993.

2. "Brazil Biomass Integrated Gasification/Gas Turbine Project," Global Environment Facility, United Nations Development Program, New York, 1993.

3. "Renewable Energy Technology Characterizations," Joint Report, EPRI and U.S. Department of Energy, EPRI TR-109496, December 1997.

4. "Brazil Hydro and Thermal Power Sector Study," Joint United Nations Development Program/World Bank, Report No. 197/97, September 1997.

5. "BIOPOWER: Biomass and Waste Fuel Power Plant Performance and Cost Model," EPRI TR-101774, March 1985.

6. "TAG™ - Technical Assessment Guide, Volume 1: Electricity Supply—1993," Revision 7, Electric Power Research Institute, Palo Alto, CA, EPRI/TR-102276-V1R7, 1993.


subfoot1.gif (2102 bytes)