00:00 In this training video,

00:01 we will show you how to use the contract management plan to manage the contract.

00:07 The previous module,

00:08 completing the contract management plan,

00:11 covered how the appointed contract manager finalized the plan by recording.

00:16 The actual dates for key contract implementation

00:19 milestones or stages as they are completed.

00:23 The contract key performance indicators where applicable,

00:27 the planned deliverables under the contract and their expected timing,

00:31 and the planned payments to suppliers,

00:34 contractors,

00:35 consultants and their expected timing.

00:38 Upon successfully completing all these actions,

00:41 a contract management plan was generated by clicking the finalized

00:45 button on the top right side of the screen.

00:48 This brings us to the final module on using

00:51 the contract management plan to manage the contract.

00:55 At the end of this module,

00:57 you should be able to manage the contract by tracking and recording the following.

01:02 Continuing to record the actual dates for key contract

01:06 implementation milestones or stages as they are completed,

01:10 including recording major contract events,

01:13 the measured KPI against the target for the relevant period,

01:18 the actual dates for receipt of the deliverables,

01:21 the actual amounts and dates for each of the payments.

01:25 Please note that as explained in the previous module,

01:28 the actual dates should be recorded as and when they occur.

01:32 The contract management system provides alerts and

01:35 reminders via email of upcoming or overdue deliverables

01:39 based on the planned dates specified for

01:41 each of the key milestones or deliverables.

01:45 These alerts are designed to assist you to track each of the milestones

01:49 and ensure that they are performed as contracted and that where necessary,

01:53 any corrective action is taken on time.

01:58 You can now go to the contract management plan to record the actual events and dates.

02:04 We will demonstrate the process using an example of a contract for

02:09 purchasing motor vehicles which are to be delivered in 2 batches.

02:13 1.

02:14 Recording the actual dates for key contract implementation

02:18 milestones or stages as they are completed.

02:21 Go to the relevant stage of the roadmap and record

02:24 the actual date for completion of a key milestone.

02:28 2,

02:29 recording major contractual events as they occur.

02:33 Record the actual dates as they

02:35 keep occurring during the contract implementation.

02:38 For example,

02:39 in this milestone in blue,

02:41 if a contract during implementation requires to be amended,

02:45 you will be required to upload the amendment along with actual dates.

02:50 Similarly,

02:51 during the completion stage,

02:52 use the active fields to fill in the required information.

02:57 For contract completion,

02:58 you will be required to record the actual date of completion,

03:02 upload mandatory and or supporting documents,

03:05 and notify the bank team for contracts subject to prior review.

03:11 3,

03:11 recording the measured KPI against the target for the relevant period.

03:16 As the KPIs begin to show the fields for actual time period,

03:21 you should record the actual measured indicator for the set period.

03:26 Note that just the number should be recorded and the unit of measure need not

03:30 be added in order to enable the system to add the cumulative total where relevant.

03:37 4,

03:38 recording the completion of deliverables.

03:40 Similarly,

03:41 for deliverables milestones,

03:43 you will be able to see the fields to record actual completion dates.

03:57 Fields will remain open for recording the actual dates as and

04:01 when they occur for deliveries that are yet to be made.

04:14 5.

04:14 Recording contract payments.

04:16 The final stage is recording the payments under the payment tab.

04:21 Clicking on the payments tab shows the payments plan.

04:24 Note that the payments plan indicates the status of the payment,

04:28 including whether it is overdue or upcoming with

04:30 the overdue payments marked with a red indicator.

04:34 The payments plan also shows the actual date of completion of

04:37 a delivery or milestone as already recorded in the deliverables tab.

04:43 It is therefore important that you record completed deliverables in

04:47 that tab before recording the payments in the payments tab.

04:51 To make edits to the payments,

04:53 click on the pencil button.

04:55 This will open a pop-up window and show information

04:58 for payments that have been made or actions taken.

05:02 Please note that some of the fields like deliverable milestone names,

05:06 plan date,

05:07 linkage to roadmap and currency are not active because they

05:11 were recorded and fixed at the contract management plan phase.

05:18 You can only enter data in the active fields for payment date,

05:22 amount,

05:22 certificate number,

05:23 and provide comments.

05:30 For payments that have been paid,

05:32 the payment status will show paid.

05:35 For deliveries that have not been made yet,

05:37 the payment status will show upcoming initially,

05:41 then will change to overdue after the payment date has passed.

05:45 This is an indication that an action needs to be taken.

05:48 You will also receive alerts at various stages as reminders.

05:53 Once all the payments have been made,

05:55 the status should show as paid against each deliverable.

05:58 The KPI must be filled as the payments are being

06:01 made to know the financial progress of the contract.

06:06 This brings us to the end of managing the contract using contract management plan.

showAllTimestamps
no
transcript
In this training video, we will show you how to use the contract management plan to manage the contract. The previous module, completing the contract management plan, covered how the appointed contract manager finalized the plan by recording. The actual dates for key contract implementation milestones or stages as they are completed. The contract key performance indicators where applicable, the planned deliverables under the contract and their expected timing, and the planned payments to suppliers, contractors, consultants and their expected timing. Upon successfully completing all these actions, a contract management plan was generated by clicking the finalized button on the top right side of the screen. This brings us to the final module on using the contract management plan to manage the contract. At the end of this module, you should be able to manage the contract by tracking and recording the following. Continuing to record the actual dates for key contract implementation milestones or stages as they are completed, including recording major contract events, the measured KPI against the target for the relevant period, the actual dates for receipt of the deliverables, the actual amounts and dates for each of the payments. Please note that as explained in the previous module, the actual dates should be recorded as and when they occur. The contract management system provides alerts and reminders via email of upcoming or overdue deliverables based on the planned dates specified for each of the key milestones or deliverables. These alerts are designed to assist you to track each of the milestones and ensure that they are performed as contracted and that where necessary, any corrective action is taken on time. You can now go to the contract management plan to record the actual events and dates. We will demonstrate the process using an example of a contract for purchasing motor vehicles which are to be delivered in 2 batches. 1. Recording the actual dates for key contract implementation milestones or stages as they are completed. Go to the relevant stage of the roadmap and record the actual date for completion of a key milestone. 2, recording major contractual events as they occur. Record the actual dates as they keep occurring during the contract implementation. For example, in this milestone in blue, if a contract during implementation requires to be amended, you will be required to upload the amendment along with actual dates. Similarly, during the completion stage, use the active fields to fill in the required information. For contract completion, you will be required to record the actual date of completion, upload mandatory and or supporting documents, and notify the bank team for contracts subject to prior review. 3, recording the measured KPI against the target for the relevant period. As the KPIs begin to show the fields for actual time period, you should record the actual measured indicator for the set period. Note that just the number should be recorded and the unit of measure need not be added in order to enable the system to add the cumulative total where relevant. 4, recording the completion of deliverables. Similarly, for deliverables milestones, you will be able to see the fields to record actual completion dates. Fields will remain open for recording the actual dates as and when they occur for deliveries that are yet to be made. 5. Recording contract payments. The final stage is recording the payments under the payment tab. Clicking on the payments tab shows the payments plan. Note that the payments plan indicates the status of the payment, including whether it is overdue or upcoming with the overdue payments marked with a red indicator. The payments plan also shows the actual date of completion of a delivery or milestone as already recorded in the deliverables tab. It is therefore important that you record completed deliverables in that tab before recording the payments in the payments tab. To make edits to the payments, click on the pencil button. This will open a pop-up window and show information for payments that have been made or actions taken. Please note that some of the fields like deliverable milestone names, plan date, linkage to roadmap and currency are not active because they were recorded and fixed at the contract management plan phase. You can only enter data in the active fields for payment date, amount, certificate number, and provide comments. For payments that have been paid, the payment status will show paid. For deliveries that have not been made yet, the payment status will show upcoming initially, then will change to overdue after the payment date has passed. This is an indication that an action needs to be taken. You will also receive alerts at various stages as reminders. Once all the payments have been made, the status should show as paid against each deliverable. The KPI must be filled as the payments are being made to know the financial progress of the contract. This brings us to the end of managing the contract using contract management plan.
showAllTranscripts
no
duration
PT6M18S
scene7File
worldbank/today STEP - Using the Contract Management Plan - Final Full Video
scene7Domain
https://worldbank.scene7.com/
scene7FileAvs
worldbank/today STEP - Using the Contract Management Plan - Final Full Video-AVS
title
today STEP Using the Contract Management Plan Final Full Video
description
today STEP Using the Contract Management Plan Final Full Video
showTimestampAndTranscript
yes
col-xs-12
col-sm-12
col-md-3
col-lg-3
col-xs-12
col-sm-12
col-md-7
col-lg-7
  • add-style
  • lp-body-content