Performance-based Contracting for Roads in Brazil
| 1. Country |
Brazil |
| 2. Year when the
first performance-based contract was awarded |
A pilot contract was awarded in 1997 |
| 3. What government
organization promoted/initiated a PBC approach in the country? |
Departamento Nacional de Estradas de Rodagem (DNER) - (National
Roads Department) |
| 4. What were the
reasons for switching from the traditional unit price-based
to PBC
for road maintenance? |
(1) Difficulty
to supervise and administer too many admeasurement contracts;
(2) Fiscal constraints:
MoF tended to allocate only a portion, e.g. 60%, of the
budget approved by the Congress, insufficient to cover
all road needs;
(3) transfer some
risk of design to the contractor;
(4) let DNER have
more flexibility
(5) See more in the Additional
Comments. |
| 5. Name of the organization
that is currently in charge of management of road maintenance |
DNER |
| 6. Supervision of
the contractors is done by |
Local consulting firm |
| 7. Sources of the
current funding of PBC |
External
funding (WB and Inter-American Development Bank)
Central
funding
|
| 8. Number of contractors
currently executing PBCs |
80 contactors.
Subcontracting to small contractors is very common, especially when the contractor
is based, e.g. in the North of the country, but the contracted area is in the
South. |
| 9. Cost per km per
year |
It varies from $ 20,000 to 70,000 per km per contract |
| 10. The contract
size (km) |
100-700 km |
| 11. Dispute resolution
mechanism |
The parties try to use:
Mutual consultation/direct
negotiation (site inspection, progress meetings and collaborative
discussions of each party’s position);
Arbitration (e.g., Dispute
Review Board). |
| 12. Procurement
process applied |
International Competitive Bidding, but foreign
contractors are not interested as they do not see much scope
to submit bids lower than those of local contractors. |
| 13. Was prequalification
used? |
No, because activities outsourced under PBC are
the simplest civil works. |
| 14. Payment mechanism
for some services |
Rehabilitation is paid based on the number of
km rehabilitated. |
| 15. Types of delivery
services under lump sum payment |
Rehabilitation and routine maintenance |
| 16. Types of roads
covered under PBC |
Federal highways and state roads |
| 17. Percentage of
this type of road in the entire network under PBC |
9.5%
or 6,393 km of 67,000 km of the federal highway network
10.5%
or 2,104 km of 199,000 km the state highway network |

Reasons of switching from the traditional unit price-based to PBC
of road maintenance
Prior to 1970, the routine maintenance of the federal highway system
was carried out directly by DNER using its own personnel and equipment.
However, because of the large maintenance backlog accumulated over
20 years, as higher priority was given to paving and new construction,
labor shortages and insufficient maintenance equipment in the field
residencies made it impossible for DNER to continue routine maintenance
exclusively by force-account. In 1975, in addition to reorganizing
and structuring a limited core of force-account unit, DNER shifted
its policy to maintenance by contract, and, where appropriate, to
delegation of these activities through agreements with State Highway
Departments, or exceptionally with the Army. In 1990, the distribution
between the three types of maintenance were as follows: contract
maintenance 60%, delegated maintenance 25%, and force-account maintenance
15% of the total length of the federal network.
To a large extent, till 1995, the 25-year experience with maintenance
by contract has been successful, and today 80% of the federal system
(excluding 13,000 km of earth roads) i.e., about 44,000 km, are being
maintained through individual three-years contracts with private
contractors.
These admeasurement-type contracts, however, are becoming more and
more difficult to manage, not only in the preparation stage, but
also during execution. Items to be quantified and measured for payments
sometimes reach 200 to 300 in number, and DNER lacks personnel to
supervise efficiently the quantity and quality of the works performed
by the contractors on site. Therefore, there is a growing tendency
to measure and monitor on a sample basis with all the shortcomings
and uncertainties that such a system entails. The situation is further
compounded by the deficiencies in resource allocations: not only
do maintenance budgets tend to be insufficient, but activities are
difficult to plan and program since resources are released by the
Treasury on an unpredictable basis.
The need was therefore felt to go one step further in order to improve
the system and to ensure better service to road users. Solutions
had to be sought to the problem of cumbersome measurements and supervision
procedures by DNER, while attending the necessity to bestow more
responsibility and initiative to the contractors. To that effect,
DNER has envisaged the possibility of adopting performance-type contracts
that are already being implemented with success in Argentina. These
would make it possible to reduce considerably the work-force needed
for preparation and supervision, while allowing the contractors to
be more creative and more directly involved in the design and quality
control of the maintenance program.
One system concerns essentially routine maintenance and applies
to roads in good to regular condition. The other system, which integrates
both rehabilitation and routine maintenance, applies to small networks
in regular to bad condition, necessitating some prior strengthening
or resurfacing works before routine maintenance can be effectively
carried out. The first system would normally be awarded for a period
of 5 to 10 years. The contracts would not define the type and quantities
of works to be executed and paid on a unit price basis, but rather
a desired level of service. The performance categories include, for
example, the riding quality of the pavement, the presence and efficiency
of drainage and safety features, or the friendliness of the road’s
immediate environment. Payments would be made on a km/month basis,
following regular inspections carried out to identify any deficiencies
which, unless corrected within a given time period, would give rise
to penalties, that would be deducted from the payments to be made
to the contractors. The second system (integrated rehabilitation
and maintenance) comprises initially a rehabilitation component paid,
upon execution, on a lump-sum basis, provided the specified results
are achieved. The rehabilitated network would then be maintained
according to the km/month system.
 Lessons learnt
- Restraint should
be used in the selection of contractual performance indicators. The DNER started with too many performance indicators,
which placed a heavy load on supervisors. Later on, having gone
through a priority-setting exercise, the list of indicators was
reduced.
- Design of penalty mechanism should
take into consideration the culture of the country. In the course of the program, it
was noticed
that Brazilians are reluctant to pay fines. For this reason,
in the second round of PBCs, a modified penalty mechanism was
introduced:
suspension of a specific amount in the monthly payment in case
of non-compliance and further subtraction of this amount from
the monthly
payment if corrective measures have not been undertaken.
- Longer term contracts, e.g. 5
years, should be used. Short-term
contracts (e.g. 1-year long) made it hard for contractors
to survive when their payments were delayed.
Sources:
- World Bank. 1997. “Staff Appraisal Report: Brazil – Federal
Highway Rehabilitation and Decentralization Project.” May
20, 1997. Infrastructure and Urban Development Division. Latin
America
and the Caribbean Regional Office. Washington, D.C.: World Bank.
Available at: http://wwwwds.worldbank.org/servlet/WDS_IBank_Servlet?pcont=details&eid=000009265_3970818102345
- Interview with Aymeric-Albin Meyer, Sr. Transport Specialist,
World Bank Latin America Region. April 2005.
Back to Case
Studies

|