Unit Costs of Road Works as contained in the
Latvian Road Administration Progress Report for June 1999
|
Pavements |
Unit |
US$1 |
|
Pothole patching |
- |
t |
70.31 |
|
Pothole patching |
- |
m2 |
8.50 |
|
Pothole patching |
- |
m |
9.08 |
|
Crack sealing with bitumen |
- |
m2 |
1.22 |
|
Crack sealing with bitumen |
- |
m |
1.03 |
|
Tack coating |
- |
m2 |
0.31 |
|
Milling of asphalt concrete joints |
- |
m2 |
3.58 |
|
Milling of asphalt concrete pavement |
- |
m2 |
2.31 |
|
Cold recycling | 6 cm |
m2 |
2.75 |
|
Depression filling |
- |
t |
39.42 |
|
Asphalt concrete leveling course construction |
- |
t |
45.34 |
|
. |
3 cm |
m2 |
3.17 |
. |
4 cm |
m2 |
4.22 |
| - |
6 cm |
m2 |
6.59 |
- |
7 cm |
m2 |
7.71 |
|
Asphalt wearing course construction |
- |
t |
50.05 |
- |
3 cm |
m2 |
3.66 |
- |
3.5 cm |
m2 |
4.27 |
- |
4 cm |
m2 |
4.86 |
- |
5 cm |
m2 |
6.07 |
- |
6 cm |
m2 |
7.31 |
|
Asphalt concrete bottom course construction |
- |
t |
48.12 |
- |
5 cm |
m2 |
5.59 |
- |
6 cm |
m2 |
6.71 |
|
Remix Plus technology (milling+hot mix) |
- |
m2 |
5.15 |
|
Single surface dressing |
- |
m2 |
1.58 |
Double surface dressing |
- |
m2 |
2.66 |
| 1Exchange rate used: US$1=0.59 LVL |
|