Vietnam’s shift from a centrally planned to a market economy has transformed the country from one of the poorest in the world into a lower middle-income country. Vietnam now is one of the most dynamic emerging countries in East Asia region. Read More »
Ratings for the Community Based Rural
Infrastructure Project for Vietnam were as follows: outcomes
were satisfactory, the risk to development outcome was
moderate, the... Show More + Bank performance was satisfactory, and the
Borrower performance was also satisfactory. Some lessons
learned included: the manual processing of data has
influenced the project throughout implementation. The
absence of an automated Management Information System (MIS)
led to enormous staff time undertakings to track project
progress. Lack of a verifying mechanism to confirm data
accuracy also created confusion at all levels. The data
source is not organized in a way to measure project impacts
and makes it difficult to extract useful data. The
counterpart agency should be more active in establishing a
good MIS at the early stage of project implementation. The
project should be provided with more technical assistance on
Monitoring and Evaluation (M&E) throughout project
implementation. The project design clearly recognized the
long-standing top-down planning and management approach at
the counterpart agencies. The design includes an alternative
mechanism to foster decentralization, but it did not
demonstrate a road map to scale up the project outcomes into
the government's system. The project's
decentralized approach faced a lot of criticism during
project preparation and it was already difficult for the
project preparation team to lay out a design to mainstream
the decentralized approach into national policy. The
Project's decentralized approach was accepted by the
government because it was a project to first demonstrate
success and then scale up on the basis of the results. Lack
of a design to scale up project outcomes at the national
level inhibits the counterpart agency from further
integration of project achievements into the government
system. When preparing a pilot project as this one, it is
important to conduct a careful analysis and design
concerning political circumstances, and include when and how
project outcomes will be integrated into national policy. Show Less -
Date: March 1, 2010
Report#: ICR1293
Document Type: Implementation Completion and Results Report