The project ( $ 15 million plus another $18 million - 1999-2003 ) had
four objectives : (i) improved access of poor rural populations to social
and economic infrastructure; (ii) on a pilot basis, empowerment of poor
rural communities and/or communes to identify, organize, manage funds
and implement sub-projects responsive to community needs; (iii) employment
creation; and (iv) increased capacity of the private sector, local small
contractors, artisans, skilled labor, and NGOs.
Madagascar was struck by a series of cyclones that damaged
basic infrastructure over the first three months of 2000. As part of
the multi-pronged approach to assist the country in its rehabilitation
efforts, in July 2000, the World Bank’s Board approved a Supplemental
Credit of $18 million – there was no change, however, in the project’s
original objectives.
Impact on the ground
•
The FID ( Fonds d’intervention pour le developpment ) constructed
337 classrooms, slightly under its target of 358 ; the 34 classrooms
rehabilitated exceeded the target of 32. It constructed266 health
centers, falling short of the target of 292, but exceeded its target
of wells by constructing 175 – 10 more than the original target.
The market projects surpassed the target by 12 with 97 buildings.
•
FID analysis of pre- and post-project outcomes for 6 types of infrastructure
projects in all 6 provinces yielded the following information. The
total number of students enrolled in beneficiary schools increased
from 10,499 to 21,623; the average rate of exam success in participant
primary schools was higher – 59.21% - than before – 35.81%,
as was that for participant secondary schools – 49.75% compared
to 31.16%; The total number of annual consultations at beneficiary
health posts was higher – 79,848 – compared to 47, 482,
as was the total number of children vaccinated – 20,059 compared
to 8,588; more persons used wells - 49,590. compared to 36,970. For
irrigation projects, the production of rice was higher – 4,489
tons per year versus 3,846; more beneficiaries used the irrigation
systems – 4,202 – compared to 3,846 and there were two
annual yields as opposed to one; finally, the total number of vendors
in markets installed rose from 2,338 to 3,880.
•
The project financed 565 capacity building sub-projects for rural
communities, local associations, communes, local contractors, artisans
and NGOs. Training was provided to 550 rural communities and communes,
92 micro-enterprises, 115 engineering consulting firm consultants
and 257 NGOs.
•
The impact on capacities, both in the private sector, and at the local
level, was substantial. In the former, the FID contributed to the
emergence of a large number of contractors who specialized in delivering
services in rural areas and in the context of local development initiatives.
About 100 local engineering consulting firms undertook feasibility
studies on approved sub-project requests and drew up execution plans
and studies, and 349 local enterprises implemented the works on-site.
Today, this pool of expertise is available to and tapped by the FID
and other donors.
•
At the local level, the emergence of local water associations is particularly
remarkable. For schools, parent’s associations were effectively
incorporated and played a major role by participating in sub-project
activities from the formulation of requests to the completion of the
infrastructure. Based on the success of its pilot, FID now involves
communes and community associations in the procurement and supervision
of investments on a larger scale under the Community Development project.
The pilot also introduced municipal planning exercises, which is today
a standard practice for all donor investments at the commune level.
•
The Beneficiary Assessment financed by the project helped strengthen
the capacity of members of the sub-project cells, communes and other
partners; the technical audit carried out helped improve the quality
of the infrastructure and rectify certain technical defects in the
completed civil works; the financial audits ( 3 ) helped to improve
and strengthen internal control systems such as procurement procedures,
management procedures and accounting.
•
Targeting. More attention needs to be paid to improve targeting even
when poverty is pervasive. An important factor here is the application
of transparent and objective selection and allocation criteria. When
no poverty map is available, a standard allocation formula for districts
and communes, based on simple criteria such as population size, can
be introduced as this would increase predictability for local governments
and communities.
•
Monitoring and evaluation. The lack of counterfactual and baseline
data present challenges for analyzing impact. Good data collection
needs to be combined with good methodology and a clear evaluation
strategy. The sustainability issue cannot be addressed without empirical
evidence.
•
Sustainability. Creating maintenance committees is not sufficient
to ensure sustainability of community sub-projects. Social funds should
develop more binding agreements and cooperative arrangements with
line agencies in this regard.
•
Co-ordination with other Bank operations. While the framework for
coordination of the FID with rural projects was agreed upon and put
in place, there was no follow-up. There should be a permanent coordination
mechanism to maximize synergies between projects.
•
Donor coordination. Fragmented CDD ( Community Driven Development
) donor programs have the tendency to drive local government agendas
rather than support them. More government involvement and clearer
policy guidance would help considerably to resolve this issue.